Maintenance & Grounds

Longterm Facility Maintenance Project Summaries

In 2016, the Minnesota State legislature passed the Longterm Facilities Maintenance Revenue (LTFMR) for public school districts, charter schools, intermediate districts and cooperative units to address:

1. Deferred capital expenditure and maintenance necessary to prevent further erosion of facilities
2. Approved Health and Safety Capital Projects
3. Increased accessibility to school facilities
4. Transfers from the LTFMR reserve in the general fund to the debt redemption fund (by board resolution)
5. Approved expenditures associated with remodeling instructional space for Voluntary Pre-K programs
6. Charter schools are allowed to use the revenue for any purpose related to the school.

All participants in the LTFMR program must have a 10-year facilities plan. The plan must be updated annually and approved by both the school's governing board and Commissioner of Education.

Voter-approval is not required for issuance of general obligation bonds for LTFMR projects.

Read more LTFMR in Financing Education in Minnesota 2016-17.

Proposed and completed LTFMR projects

Cedar Creek Community School

2016

Parking lot replacement (one section)

2017

HVAC system updates (boiler plant, ventilation, building controls)

2018

Interior work (restroom renovation)

Crossroads School & Vocational Center

2016

No large projects scheduled.

2017

HVAC system updates (ventilation replacement, building controls)

2018

Interior work (carpet replacement)

Districtwide deferred maintenance measures

2016-2018

Paved surface repairs
Interior lighting
Exterior lighting/site lighting
Flooring/VCT
Building envelope sealing
Painting
Interior and exterior doors
Clock and PA system replacements
Mechanical repairs

East Bethel Community School

2016

Roof replacement (one section)

2017

HVAC system updates (boiler plant, building controls)
Playground surface replacement
Chiller repairs

2018

Interior work (replace demountable walls, ceiling replacement)

Lifelong Learning Center

2016

Roof replacement (one section)

2017

HVAC system updates (boiler plant, building controls)

2018

Interior work (restroom renovation)
Exterior work (select window replacements)

St. Francis Elementary School

2016

Roofing replacement (one section)

2017

HVAC system updates (boiler plant, building controls)

2018

Interior work (restroom renovation, ceiling replacement).

St. Francis Middle School

2016

Roof replacement (four sections)

2017

HVAC system updates (boilers, steam line replacement, ventilation system improvements, controls)
Chiller repairs
Exterior work (select window and door replacements)

2018

Tennis court reconstruction

St. Francis High School

2016

Roof replacement (two sections)
Tennis court resurfacing

2017

HVAC system updates (boiler plant, building controls)
Water softener replacement

2018

Interior work (replace demountable walls, ceiling replacement)
Track resurfacing

Transportation Building

2016

Roofing replacement (all sections)

2017

Exterior work (replace siding)

2018

No large projects scheduled.